Client: | Redrow Homes Plc. |
Project: | Housing Development at Temple Waterfront, Strood |
Project Value: | £5.8 Million |
Project Duration: | Phase 1: 18 weeks Phase 2: 42 weeks |
Contact: | Mark Saunders |
Project Details: |
Design and install piling mat involving importation of 14,000 m3 of crushed concrete on Tensar geotextile Phase 1: Piling Design and construction of bridge to overcome bad ground at site entrance. Excavate 47,000M3 of obstructions. Crush on site and raise levels by 1.5m over whole site area. Phase 2: Construction of foundations for 44 houses and 4 apartment blocks Piling (817 No) Ground beams Gas Membrane Jet Floor Installation of all roads and drainage for the development 11 Km of service media 1000m of adoptable road Deep large bore drainage Installation of 6m deep pumping station Installation of electricity sub-station |