Client: | Inland Homes Plc. |
Project: | Housing Development at Queensgate, Farnborough |
Project Value: | £3.4 Million |
Project Duration: | Phase 1: 24 weeks Phase 2: 12 weeks |
Contact: | Garry Moore |
Project Details: |
Design and install piling mat involving importation of 14,000 m3 of crushed concrete on Tensar geotextile Phase 1: Ground Improvement to form piling mats Piling Construction of foundations for 5 Apartment Blocks Piling Ground beams Lift Pits and Block and Beam Floor Phase 2: Installation of all roads and drainage for the development Large Scale attenuation tanks 50,000 litre foul storage tank and pump. Car Parks Retaining Walls and footpaths Service Media, temporary and permanent. |