Client: | IKEA |
Project Value: | £6.5 Million |
Project Duration: | 50 weeks |
Project Details: |
Break up 5 acres of existing slabs and crush on site Excavate 5000m3 and Cart Away Piling Mat and attendance on pilers Construct underground 600m2 sprinkler tank 180Lm of 3m high RC retaining walls 150Lm of pre cast retaining walls Installation of foul and storm drainage and pumps Installation of stormcell drainage Installation of 2Km of service media with turnaround chambers Pouring of pile caps and ground beams. 10,000 m3 of concrete used in construction Construction of Service yard 2000m2 Construction of Car park including Tarmac 3000m2 |